Agenda Item Ref. #: PW101116-05

Agenda Item Title:

Approve Change Order #1F to Complete Concrete, Inc. for East Anamosa Street Pedestrian Crossing Project No. 13-2125 / CIP No. 50946 for a decrease of $11,942.00.

Origination Group:
Public Works Committee
Origination Meeting Date:
10/11/2016
City Council Hearing Date:
10/17/2016
Staff Contact:
Klare Schroeder
Agenda Item Summary:
Change Order #1F to Complete Concrete, Inc. East Anamosa Street Pedestrian Crossing Project #13-2125/CIP 50946 for a decrease of $11,942.00.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Sanitary Sewer Sanitary Sewer Improvements
Water Water Improvements
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download: