Agenda Item Title:
Approve Change order #1F for Project No. 15-2230 & 15-2251 / CIP No. 51078 & 51085 Sanitary Sewer Extension Block 33 South Boulevard Addition & Block 12 Boulevard Addition to Rapid Construction, LLC for a decrease of $1,754.55.
Origination Group:
Public Works Committee
Origination Meeting Date:
05/31/2016
City Council Hearing Date:
06/06/2016
Agenda Item Summary:
Change Order #1F Project No. 15-2230 & 15-2251/CIP No. 51078 & 51085 Sanitary Sewer Extension Block 33 South Boulevard Addition & Block 12 Boulevard Addition to Rapid Construction, LLC for a decrease of $1,754.55.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Sanitary Sewer | Improvements |
Is Funding Budgeted?:
Not Budgeted
Recommendations:
Origination Recommendation Action:
Approve