Agenda Item Title:
Authorize Mayor and Finance Officer to sign the Standard Form of Agreement Between Owner and Construction Manager as Constructor (AIA Doc. A133 – 2009) and General Conditions of the Construction Contract (AIA Doc. A201-2007) with M. A. Mortenson Company for the Rushmore Plaza Civic Center Arena Project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
The contract is divided into three parts. Mortenson received $48,000 for its preconstruction services preparing construction estimates and working with the architects on projected costs. The contract agrees to pay Mortenson $582,000 for the design & pre-construction phase of the project. At the end of the design & pre-construction phase the City will be presented with the GMP. If the City authorizes the project to proceed, Mortenson’s fee will be 3.15% of the GMP. Based on an estimated construction cost of $105 million, the fee would be approximately $3.3 million. The funding source for this contract is the Vision Account. | |