Authorize staff to advertise for bids E. Watertown St Water Main Replacement. Project #20-2501 CIP #51076. Estimated Cost $550,000.00.

Origination Group:
City Council Working Session
Origination Meeting Date:
02/10/2021
City Council Hearing Date:
02/16/2021
Staff Contact:
Michelle Lashley
Location:
Watertown St from Pine St to Riley Ave
Agenda Item Summary:
Project is being driven by the need to replace approximately 900 ft of 6" DI water main in E Watertown St from Pine St. to N Cherry Ave as well as provide a water main connection in E Watertown St between Spruce St and n Cherry Ave. Multiple water line breaks in this area and main is a dead end.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
602 0933
Is Funding Budgeted?:
Budgeted

Recommendations: