Posted: July 19, 2021
Rapid City
Agenda Item Summary

Agenda Item Ref. #: WS072821 10

Agenda Item Title:

Approve Change Order 1 to Underground Construction LLC for St Andrew Street East of Palo Verde Dr Reconstruction and Utility Project, Project #21-2604/CIP 51260 for an Increase of $10,206.00

Origination Group:
City Council Working Session
Origination Meeting Date:
07/28/2021
City Council Hearing Date:
08/02/2021
Petitioner:
City of Rapid City
Staff Contact:
Roger Hall
Location:
Saint Andrew Street
Agenda Item Summary:
Approve Change Order 1 to Underground Construction LLC for St Andrew Street East of Palo Verde Dr Reconstruction and Utility Project, Project #21-2604/CIP 51260 for an increase of $10,206.00. This change order adjusts for extra concrete removal.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Water (602) Repl/Imp (933)
Sewer (604) Repl/Imp (833)
CIP (505) Drainage (8911)
CIP (505) Streets (8910)
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download:

pdf WS072821 10 2604 CO1 (1.42 MB)