Agenda Item Title:
Approve Change Order 1 to Simon Contractors of SD Inc. for Pavement Rehabilitation Project – Forest Court, Project #2624 / CIP 50844 for an Increase of $152,602.15
Origination Group:
City Council Working Session
Origination Meeting Date:
06/30/2021
City Council Hearing Date:
07/06/2021
Petitioner:
City of Rapid City
Staff Contact:
Roger Hall
Location:
Forest Court
Agenda Item Summary:
Approve Change Order 1 to Simon Contractors of SD Inc. for Pavement Rehabilitation Project – Forest Court, Project #2624 / CIP 50844 for an Increase of $152,602.15 for changes and additions necessary to complete the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8910 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve