Agenda Item Title:
Approve change order 1 to Tru-Form Construction, Inc. for 2020 ADA Project, Project #2062 for an increase of $9,851.80.
Origination Group:
City Council Working Session
Origination Meeting Date:
04/14/2021
City Council Hearing Date:
04/19/2021
Staff Contact:
Roger Hall
Agenda Item Summary:
Approve change order 1 to Tru-Form Construction, Inc. for 2020 ADA Project, Project #2062 for an increase of $9,851.80. A failing concrete panel was discovered in the vicinity of the project.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8913 |