Agenda Item Title:
Authorize Mayor and Finance Officer to Sign an Agreement between the City of Rapid and Skyline Engineering, LLC for Construction Administration for the Downtown Lighting, Project No. 20-2613 / CIP No. 51228, in the amount of $112,705.00
Origination Group:
City Council Working Session
Origination Meeting Date:
01/27/2021
City Council Hearing Date:
02/01/2021
Staff Contact:
Roger L. Hall
Location:
Downtown Lighting Phase II
Agenda Item Summary:
Contract with previously selected consultant, Skyline Engineering, LLC, for the construction administration on the installation of decorative roadway and pedestrian lighting on St. Joseph St. and Main St. from East Blvd. to West Blvd, for the Vision Fund Downtown Lighting Project
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
107 | 132 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve