Posted: November 23, 2020
Rapid City
Agenda Item Summary

Agenda Item Ref. #: WS120220 07

Agenda Item Title:

Approve Change Order 1 to Mainline Contracting, Inc. for Northridge Booster Pump Station and Stoney Creek Booster Pump Station Improvements, Project No. 2178/CIP No. 50812.CD for an Increase of $5,711.49

Origination Group:
City Council Working Session
Origination Meeting Date:
12/02/2020
City Council Hearing Date:
12/07/2020
Staff Contact:
Roger Hall
Agenda Item Summary:
Approve change order 1 to Mainline Contracting, Inc. for Northridge Booster Pump Station and Stoney Creek Booster Pump Station Improvements, Project #2178/CIP NO.50812.CD for an increase of $5,711.49.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
602 933
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve