Posted: November 06, 2020
Rapid City
Agenda Item Summary

Agenda Item Ref. #: WS111020-06

Agenda Item Title:

Approve Change Order #1 for Fitzgerald Stadium Renovations Proj. No. 19-2508 CIP #51231 with MAC Construction for an increase of $124,557.87.

Origination Group:
City Council Working Session
Origination Meeting Date:
11/10/2020
City Council Hearing Date:
11/16/2020
Staff Contact:
Rod Johnson
Location:
Fitzgerald Stadium
Agenda Item Summary:
The major item in this change order is to add back into the contract three of the four Shade Canopy Bays that were bid but not accepted in the original contract award. This is being accomplished by Black Hills Sports accepting the majority of the cost of the synthetic turf of approximately $500,000.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
505 8912-4372
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Approve

Attachments & Links to Download:

WS111020-06 Project 2508 CO1