Posted: August 31, 2023
Rapid City
Agenda Item Summary

Agenda Item Ref. #: CC090523-04.2 St Charles Street Rehab and Water Main Replacement Project 23-2760

Agenda Item Title:

Approve award of total bid for St. Charles Street Rehabilitation and Water Main Replacement, Project No. 23-2760 / CIP No. 51409 opened on August 29, 2023 to the lowest responsible bidder, BTD Enterprises, LLC. in the amount of $354,006.61.

Origination Group:
City Council
Origination Meeting Date:
09/05/2023
Staff Contact:
Michelle Lashley
Agenda Item Summary:
This project includes the rehabilitation of the north half of the intersection of St. Charles Street and 7th Street, including pavement, curb and gutter, sidewalk and C-wall and the replacement of approximately 400 feet of 8" ductile iron water main with pvc water main, and trench patch associated with the water main replacement. This project is needed due to a water main break in the existing ductile iron water main that caused pavement failures in the vicinity of the water main break.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
602 933
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $354,006.61 to BTD Enterprises, LLC.