Agenda Item Title:
Approve award of total bid for Water and Sewer Improvement Block 13 of Boulevard Addition, Project No. 22-2699 / CIP No. 50927.1 opened on January 31, 2023 to the lowest responsible bidder, Underground Construction LLC, in the amount of $1,277,372.00.
Origination Group:
City Council
Origination Meeting Date:
02/06/2023
Staff Contact:
Brandon Quiett, PE
Agenda Item Summary:
Water and sewer improvements Block 13 Boulevard Addition. Utility improvements will be located in Quincy Street, Columbus Street, and the alley between Quincy and Columbus Streets.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
602 | 933 |
604 | 833 |
505 | 8910 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $1,277,372.00 to Underground Construction, LLC.