Agenda Item Ref. #: CC100322-04.1 - Approve bid for Saint Patrick Street Reconstruction Project 20-2582

Agenda Item Title:

Approve award of total bid for Saint Patrick Street Reconstruction – Mt. Rushmore Road to 5th Street, Project No. 20-2582 / CIP No. 51126 opened on September 27, 2022 to the lowest responsible bidder, Heavy Constructors, Inc. in the amount of $5,280,947.00.

Origination Group:
City Council
Origination Meeting Date:
10/03/2022
Staff Contact:
Sara Odden
Agenda Item Summary:
This project is for the reconstruction of St. Patrick St. from Mt. Rushmore Rd. to 5th St. (approximately 1515 linear feet of roadway). The reconstruction of St. Patrick St. is needed due to the existing condition of the pavement and underground utilities. The project includes new surfacing, curb and gutter, water main replacement, sanitary sewer main replacement and storm sewer improvements. Signal improvements at 5th & St. Patrick are also included.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
505 8910
604 833
505 8911
602 933
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $5,280,947.00 to Heavy Constructors, Inc.