Agenda Item Title:
Approve award of total bid for Spring Brook Acres Water Main & PRV Abandonment, Project No. 21-2643 / CIP No. 51262 opened on August 9, 2022 to the lowest responsible bidder, Heavy Constructors, Inc. in the amount of $2,179,210.01.
Origination Group:
City Council
Origination Meeting Date:
08/15/2022
Staff Contact:
Eduardo Lopez
Agenda Item Summary:
The project will remove the pressure reducing valve (PRV) stations within the Spring Brook Acres Subdivision. The project will also replace approximately 6,200 ft of asbestos cement water main as well as the affected service lines within the project limits.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
602 | 933 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Award
Origination Recommendation Notes:
Total Bid in the amount of $2,179,210.01 to Heavy Constructors, Inc.