Agenda Item Ref. #: CC062022-04.3 Adams Street Water Main - West Blvd North

Agenda Item Title:

Approve award of total bid for Adams Street Water Main – West Blvd North Through Allen Ave., Project No. 19-2530 / CIP No. 50960 opened on June 14, 2022 to the lowest responsible bidder, Underground Construction, LLC in the amount of $990,995.00.

Origination Group:
City Council
Origination Meeting Date:
06/20/2022
Staff Contact:
Mike Wilkening
Agenda Item Summary:
Replacement of approximately 1,150 LF of 6” ductile iron water main with 8” PVC water main in Adams St. between West Blvd North and Allen Ave. Replacement of water and sewer in the intersection of Anamosa St. and West Blvd North in advance of the DOT’s Anamosa bridge replacement project.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
604 833 / 834
602 933 / 934
505 8910
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $990,995.00 to Underground Construction, LLC.