Agenda Item Title:
Reject all bids for Enchantment Road PRV CP and Repair, Project No. 20-2590 / CIP No. 51261 opened on May 31, 2022.
Origination Group:
City Council
Origination Meeting Date:
06/06/2022
Stage 2 Group Name:
City Council
Stage 2 Meeting Date:
06/20/2022
Staff Contact:
Morgan Falcone, PE
Agenda Item Summary:
One bid was received for this project. Staff is currently evaluating available options for awarding this project. A recommendation will be prepared for the June 20, 2022 City Council Meeting.
Cathodic protection and corrosion control enhancements to the two Enchantment Pressure Reducing Valve and Sustaining Valve vaults located along Enchantment Road. These improvements are necessary for safely operating the facilities until an above grade facility can be budgeted and built.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
602 | 933 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Reject