Posted: February 17, 2022
Rapid City
Agenda Item Summary

Agenda Item Ref. #: CC022222-04.1 Trenchless Sanitary Sewer Rehabilitation Jackson Blvd No. 12-2075

Agenda Item Title:

Approve award of Base Bid plus Schedule 2 for Trenchless Sanitary Sewer Rehabilitation Jackson Boulevard, Project No. 12-2075 / CIP No. 50818 opened on February 15, 2022 to the lowest responsible bidder, Mainline Contracting Inc. in the amount of $711,262.30.

Origination Group:
City Council
Origination Meeting Date:
02/22/2022
Staff Contact:
Nicole Lecy
Agenda Item Summary:
Replacement of approximately 1800 LF of existing 10" sanitary sewer main with 12" sanitary sewer main. Sewer main replacement will be completed by pipe bursting (trenchless) methods where possible and replacement will be completed by open cut trench methods in other locations. Manholes will also be replaced.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
604 833
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Base Bid in the amount of $711,261.30 plus Schedule 2 in the amount of $1.00 to Mainline Contracting Inc.