Agenda Item Title:
Approve award of total bid for Tower Road Stabilization Project– Road Reconstruction Phase, Project No. 19-2537 / CIP No. 51254 opened on December 14, 2021 to the lowest responsible bidder, Western Construction, Inc. in the amount of $120,197.85
Origination Group:
City Council
Origination Meeting Date:
12/20/2021
Staff Contact:
Mary Bosworth
Agenda Item Summary:
Reconstruction includes grading, asphalt pavement replacement, and guardrail following the slope stabilization project that was completed in the fall of 2021.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8910 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $120,197.85 to Western Construction, Inc.