Agenda Item Title:
Authorize Staff to apply for the 2022 Bridge Improvement Grant (BIG) funds for preliminary engineering work for the Chapel Lane bridge, and to accept and administer the funds if awarded.
Origination Group:
City Council
City Council Hearing Date:
07/19/2021
Staff Contact:
Sara Odden
Location:
Chapel Lane Bridge
Agenda Item Summary:
The requested grant would cover 80% of the costs for preliminary engineering work, including a rehabilitation/replacement analysis on the Chapel Lane Bridge. Approximate project costs are as follows: Total Cost = $80,000. Grant = $64,000. City Match = $16,000
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Is Funding Budgeted?:
Budgeted