Agenda Item Title:
Approve award of total bid for St. Andrew Street East of Palo Verde Drive Street Reconstruction and Utility Project, Project No. 20-2604 / CIP No. 51260 opened on May 11, 2021 to the lowest responsible bidder, Underground Construction, LLC in the amount of $936,527.85.
Origination Group:
City Council
Origination Meeting Date:
05/17/2021
Staff Contact:
Morgan Falcone
Agenda Item Summary:
Project is a full street and utility reconstruction of St. Andrew Street East of Palo Verde Drive. This project originated due to failing water and sewer mains. Multiple water main breaks have occurred in this area making it a high priority for reconstruction. The replacement of the utilities necessitate the replacement of the street and curb and gutter.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
602 | 4381 |
604 | 4380 |
505 | 4370 |
505 | 4371 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Award
Origination Recommendation Notes:
Total Bid in the amount of $936,527.85 to Underground Construction, LLC.