Posted: October 02, 2020
Rapid City
Agenda Item Summary

Agenda Item Ref. #: CC100520-4.1 - Robbinsdale Phase 6 Parkview Reconstruction

Agenda Item Title:

Approve award of total bid for Robbinsdale Phase 6 Parkview Reconstruction, Project No. 19-2517 / CIP No. 51232-B opened on September 29, 2020 to the lowest responsible bidder, Lind-Exco, Inc. in the amount of $3,310,763.57

Origination Group:
City Council
Origination Meeting Date:
10/05/2020
Staff Contact:
Doug Noyes
Agenda Item Summary:
Reconstruction of Parkview Dr. from Fairmont Blvd. to Liberty St. and Elk St. from Anaconda Rd. to Elm Ave. Project will include replacement of the pavement, sidewalk, curb and gutter, and includes installation of sanitary sewer, water main, and new storm sewer.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
604 833
602 933
505 8910
505 8911
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $3,310,763.57 to Lind-Exco, Inc.