Agenda Item Title:
Approve award of total bid for Forest Hills Dr. & Clark St. Inlay Project, Project No. 19-2555 / CIP No. 50549 opened on June 30, 2020 to the lowest responsible bidder, J & J Asphalt in the amount of $195,863.10.
Origination Group:
City Council
Origination Meeting Date:
07/06/2020
Staff Contact:
Doug Noyes
Agenda Item Summary:
The pavement section on Forest Hills Dr. and Clark St. is recommended for rehabilitation. Project to include asphalt pavement replacement, failing curb & gutter replacement, and miscellaneous concrete work. Project to be completed by November 13, 2020.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
505 | 8910 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $195,863.10 to J & J Asphalt.