Agenda Item Ref. #: CC051820-02.3 Northridge Booster Pump Station & Stoney Creek Booster Pump Station

Agenda Item Title:

Approve award of total bid for Northridge Booster Pump Station and Stoney Creek Booster Pump Station Improvements, Project No. 14-2178 / CIP No. 50812.CD opened on May 13, 2020 to the lowest responsible bidder, Mainline Contracting, Inc. in the amount of $480,050.00.

Origination Group:
City Council
Origination Meeting Date:
05/18/2020
Staff Contact:
Morgan Falcone
Agenda Item Summary:
Project will construct improvements necessary for surge mitigation, flow monitoring as well as controls and monitoring for system components in the existing Well #12/Stoney Creek Booster Pump Station located at 2930 Catron Blvd. as well as the existing Northridge Booster Pump Station located at 1041 Sagewood St.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
602 933
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Total Bid in the amount of $480,050.00 to Mainline Contracting, Inc.