Agenda Item Title:
Approve award of total bid for Hanover Drive Drainage Crossing, Project No. 18-2460 / CIP No. 51204 opened on July 30, 2019 to the lowest responsible bidder, R.C.S. Construction, Inc. in the amount of $289,832.93
Origination Group:
City Council
Origination Meeting Date:
08/05/2019
City Council Hearing Date:
08/05/2019
Staff Contact:
Brandon Quiett
Agenda Item Summary:
Box culvert drainage crossing between Parkview Drive and Hanover Drive. Includes associated 8" water main, street paving, curb and gutter, and sidewalk.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
602 | 833 |
609 | 7402 |
505 | 8910 |
505 | 8911 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Award