Approve award of total bid for Disk Drive and Haines Avenue Intersection, Project No. 16-2347 / CIP No. 51121 opened on March 26, 2019 to the lowest responsible bidder, Tru-Form Construction, Inc. in the amount of $1,121,843.17
Origination Group:
City Council
Staff Contact:
Sara Odden
Agenda Item Summary:
Reconstruction of the intersection of Disk Drive and Haines Avenue. Improvements include water main abandonment, water main reconstruction to replace an existing undersized and ductile iron pipe with a new 12" and 10" PVC mains, sewer main replacement, the construction of an ADA compliant intersection and new signal poles.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
604 | 833 |
602 | 933 |
505 | 8910 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $1,121,843.17 to Tru-Form Construction, Inc.