Agenda Item Ref. #: CC022018-02.1 Catron Boulevard Widening

Agenda Item Title:

Approve award of total bid for Catron Boulevard Widening Project, Project No. 16-2343 / CIP No. 51115 opened on February 13, 2018 to the lowest responsible bidder, Western Construction, Inc. in the amount of $1,518,356.50.

Origination Group:
City Council
Origination Meeting Date:
02/20/2018
Staff Contact:
Todd Peckosh
Agenda Item Summary:
Project will widen Catron Boulevard to 5 lanes from Nugget Gulch to Highway 16. Note: The amount of work required to be done by Contractor has been reduced from 50% to 40% for this Project.

Funding Source & Fiscal Impact (if applicable):

Funding Cost Center
Streets 8910
Drainage 8911
Waste Water 833/834
Water 933/934
Is Funding Budgeted?:
Budgeted

Recommendations:

Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Bid in the amount of $1,518,356.50 to Western Construction, Inc.