Agenda Item Title:
Approve award of Total Bid for Rapid Valley Sanitary Sewer Bypass, Project No. 13-2076 / CIP No. 50911 opened on May 9, 2017, to the lowest responsible bidder, Rapid Construction, LLC, in the amount of $617,171.69.
Origination Group:
City Council
Origination Meeting Date:
05/15/2017
Staff Contact:
Sara Odden
Agenda Item Summary:
This project is for the construction of a trunk sewer to bypass City wastewater flows from entering the Rapid Valley sewer system. The project includes approximately 1350’ of 12"-15" sanitary sewer main.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
Wastewater Improvements | 833 |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Award
Origination Recommendation Notes:
Award: Total Base Bid in the amount of $617,171.69 to Rapid Construction, LLC.