Agenda Item Title:
Approve award of Total Bid for Pavement Rehabilitation Project – Back Nine, Pebble Beach and Jolly Lane, Project No. 15-2301 / CIP No. 50844 opened on June 28, 2016 to the lowest responsible bidder, J&J Asphalt Company in the amount of $250,859.20.
Origination Group:
City Council
Origination Meeting Date:
07/05/2016
Staff Contact:
Sara Odden
Agenda Item Summary:
Mill and overlay asphalt street, remove and replace asphalt street, spot repair curb and gutter, ADA compliant intersections.
Funding Source & Fiscal Impact (if applicable):
Funding | Cost Center |
---|---|
8910 | |
Is Funding Budgeted?:
Budgeted
Recommendations:
Origination Recommendation Action:
Approve
Origination Recommendation Notes:
Award: Total Base Bid in the amount of $250,859.20 to J&J Asphalt Company.