| Project Name | Project Number | Department | Scope | Design and Inspection | Project Status | 2007 Estimated Cost |
| 1st St. and Philadelphia Sewer Main Replacement | 50579-1443 | Water Reclamation | Construction | Consultant | Design 4-16-07 - Constr. 11-30-07 | $130,000 |
| 42" Trunk Sewer Siphons Rehabilitation | 50327-1544 | Water Reclamation | Construction | Consultant | Construction Complete 5-04-07 | $1,100,000 |
| 43rd Court Watermain Reconstruction | 50606-1529 | Water | Construction | Consultant | Design 4-25-07, Constr. 9-07-07 | $890,000 |
| 44th St. Reconstruction; W. Chicago to W. Main | 50365-1435 | Streets | Design | Consultant | Design Complete 10-19-07 | $55,000 |
| Anamosa St Reconstruction, Lacrosse to Milwaukee | 50518-1471 | Streets | Construction | Consultant | Design 3-12-07, Const. 11-26-07 | $1,553,000 |
| Anamosa Street Reconstr, Wood/Willsie to Haines | 50519-1472 | Streets | Design | Consultant | Design Complete 11-07-07 | $120,000 |
| Auto Irrigation - Various Locations | 50097 | Govt. Buildings | Design/Const. | In-house | Const. Adv 4-03-07, Compl. 7-31-07 | $35,000 |
| Bicycle Path Repair | 50538-1622 | Parks & Recreation | Construction | In-house | Construction Complete 6-05-07 | $12,530 |
| Block 12, Millard Addition Sewer Extension | 50670-1625 | Water Reclamation | Design/Const. | In-house | Construction Bid letting 2-17-07 | $60,000 |
| Block 4 Alley Paving | 50297-1603 | Streets | Design/Const. | In-house | Bid 3-20-07, Const. 7-06-07 | $50,000/Assess |
| Camp Rapid Water Main | 50598-1562 | Water | Construction | Consultant | Construction Complete 6-14-07 | $1,137,000 |
| Canyon Lake Park Improvements (lighting) | Parks & Recreation | Consultant | Design Complete 2-26-07 | $160,000 | ||
| Canyon Lake Park Restoration | 50631-1561 | Public Works | Construction | Consultant | Construction Comp. 5-02-07 | $390,250 |
| Cemetery Road Paving & Irrigation | 50090-1629 | Parks & Recreation | Design/Const. | In-house | Construction Complete 6-15-07 | $40,000 |
| Chip Seal Streets | 50584-1628 | Streets | Design/Const. | In-house | Construction Complete 9-04-07 | $75,000 |
| City Street Light Maintenance Contract | NA-1618 | Streets | Construction | In-house | On-Going | |
| Civic Center Expansion | 1555 | Gov't. Buildings | Construction | Consultant | Construction through 12-2008 | $25,100,000 |
| CLD/SLR Irrigation | 50600-1515 | Parks | Construction | In-house | Design Bid 6-07-07, Const. 4-08-07 | $141,800 |
| Country Road Lift Station Improvements | 50376-1255 | Water Reclamation | Construction | Consultant | Const. Comp. 8-03-07 | $900,000 |
| Creek Drive Bridge Replacement | 50309-1241 | Streets | Construction | Consultant | Adv. 4-03-07, Const. 11-26-07 | $1,158,690 |
| Cross Street Railroad Crossing | 50172-1540 | SDDOT | Construction | In-house | Bid 6-20-07, Const. 8-30-07 | $16,000 |
| Dahl Fine Arts Expansion | 1367 | Gov't. Buildings | Construction | Consultant | Construction Bid 3-15-07 | $5,000,000 |
| Deerfield Outlet Pipe Coating | 50652-1586 | Water | Construction | Consultant | USBR Construction Bid 3-01-07 | $100,000 |
| Design Criteria Manuals | 50574-1446 | Public Works | Design | In-house | In Progress | $0 |
| Dover Drainage Improvements | 50025-1452 | Drainage | Design | Consultant | Consultant Selection 5-21-07 | $56,000 |
| Downtown Alleys Reconstruction | 50379-1627 | Streets | Design/Const. | In-house | Bid 4-10-07, Const. 8-07-07 | $50,000 |
| Downtown Area Improvement Project - Phase 1 Const. | 50627-1077 | Streets | Construction | Consultant | Phase 1 Complete 6-01-07 | $2,794,000 |
| Drainage Basin Overview Report | 50665-1614 | Drainage | Design | Consultant | Report Complete 5-11-07 | $50,000 |
| E. 53rd. St, Hwy 44 to Twilight Dr. | 50168-1503 | SDDOT | Oversight | Consultant | Design 3-03-07, Const. 12-20-07 | $2,809,000 |
| E. Anamosa Extension, E. North to Lacrosse | 50316-1397 | Streets | Construction | Consultant | Design 2-26-07, Const. 10-25-07 | $10,770,000 |
| E. Mall Drive Extension, Ph 3, LaCrosse to E. North | 50521-1334b | Streets | Design/Const. | Consultant | Consultant Selection 2-05-07 | $7,070,000 |
| Project Name | Project Number | Department | Scope | Design and Inspection | Project Status | 2007 Estimated Cost |
| E. Meade Street Reconstruction - Phase I | 50145-1333b | Streets | Construction | Consultant | Construction Complete 5-25-07 | $2,322,763 |
| E. Meade Street Reconstruction - Phase II | 50145-1333c | Streets | Design | Consultant | 2008 Project | $50,000 |
| East Franklin St. Sanitry Sewer | 50648-1557 | Water Reclamation | Construction | In-house | Const. Complete 6-04-07 | $88,000 |
| East Highway 44 and Elk Vale Watermain Loop | 50371-1248 | Water | Construction | Consultant | Construction Complete 5-21-07 | $820,000 |
| Eglin St. Reconstruction @ E. North | 50560-1470 | Streets | Design/Const. | Consultant | Construction Complete 4-02-07 | Developer |
| Elk Street Drainage Improvements | 50597-1621 | Drainage | Design/Construction | In-house | Design 3-03-07, Constr. 5-31-07 | $187,000 |
| Elk Vale Rd., I-90 to City Limits - Exit 61 | 50143-1502 | Streets | Design/Const. | Consultant | Construction Complete 8-02-07 | $350,000 |
| Elk Vale Water Reservior | 50474-1638 | Water | Design | Consultant | Consultant Approval 3-19-07 | $3,750,000 |
| Elm Ave. Watermain Rehabilitation | 50480-1517 | Water | Design | Consultant | Complete 3-30-07 | $108,000 |
| Farnwood/Rapp/Anamossa Intersection Improvements | 50286-929 | Streets | Design | Consultant | On Hold | $300,000 |
| Fire Department Burn Building | Gov't. Buildings | Construction | In-house | Construction Comp. 7-31-07 | $500,000 | |
| Fire Station | Govt. Buildings | Consultant | Land Acquisition | $150,000 | ||
| Fitzgerald Yardwaste Improvements | 1448 | Solid Waste | Construction | In-house | Const. 10-07-07 | $100,000 |
| Geotechnical Investigations Program | 50592-1605 | Public Works | Design | Consultant | On-Going | $20,000 |
| Golf Course Maintenance Building | 50515-1551 | Parks | Design | Consultant | Design Complete 5-31 | $750,000 |
| Hall Street Sanitary Sewer Extension | 50632-1482 | Water Reclamation | Construction | In-house | Construction Comp. 5-15-07 | $37,000 |
| Hwy 44 Reconstruction, from PCC Pave. to Airport | 50479-1469 | SDDOT | Construction | Consultant | Adv. 3-06-07, Const. 12-11-07 | $7,498,000 |
| Jackson Springs Water Treatment | 50570-1425 | Water | Design/Const. | Consultant | Consultant Selection 3-22-07 | $42,500,000 |
| Jolly Lane Reconstruction, Hwy 44 to Back Nine Dr | 50428-1508 | Streets | Design | Consultant | 2008 Project | $65,000 |
| Kepps Water Main Extension | 50625 | Water | Design/Const. | Consultant | Consultant RFP's Due 2-19-07 | $595,000 |
| Knollwood Outfall, Elements 2 & 20 | 50312-1390 | Drainage | Design/Const. | Consultant | Consultant Selection 4-12-07 | $80,000 |
| Lacrosse/Philadelphia Drainage Improvements | 50438-1157 | Drainage | Design | Consultant | Design Complete 8-21-07 | $16,000 |
| Lemmon Ave. Reconst., College to Monroe | 50120-1438 | Drainage | Construction | Consultant | Construction Complete 5-03-07 | $1,200,000 |
| Mall Dr Watermain Loop | 50344-1260 | Water | Construction | In-house | Bid 4-10-07, Const. 6-18-07 | $1,200,000 |
| Materials Investigation/Testing Program | 50591-1606 | Public Works | Design | Consultant | On-Going | $2,000 |
| Memorial Pk & Farlow Watermain Reconstruct | 50465-1631 | Water | Design | Consultant | Consultant Selection 3-26-07 | $1,800,000 |
| Metering Dam Expansion, SLR & Minnewasta | 50384 | Drainage | Design | Consultant | Const. Adv. 2-15-07 Compl. 7-31-07 | $65,000 |
| Mill & Overlay, Various Locations | 50549-1640 | Streets | Design/Const. | In-house | Construction Complete 4-07-07 | $300,000 |
| Milo Barber Building ADA Upgrade | Gov't. Buildings | Design | Consultant | Consultant Interviews 2-27-07 | Unknown | |
| Miscellaneous Improvement Projects (MIP) | 50298-1612 | Streets | Design/Const. | In-house | Bid 8-07-07, Const. 10-02-07 | $50,000 |
| Mt View Reconst., RR to Jackson Blvd | 50350-1342 | SDDOT | Construction | Consultant | Construction Complete 7-30-07 | $800,000 |
| Project Name | Project Number | Department | Scope | Design and Inspection | Project Status | 2007 Estimated Cost |
| Neighborhood Mill and Overlays | 50636-1608 | Streets | Design/Const. | In-house | Construction Complete 6-21-07 | $300,000 |
| North Deadwood Ave. Area Sewer Extension | 50315-1258 | Water Reclamation | Construction | Consultant | Const. Adv. 1-27-07 Compl. 8-03-07 | $850,000 |
| Omaha/Mt. View Detention pond | 50528-1391 | SDDOT | Construction | Consultant | Construction Complete 7-02-07 | |
| Out-of-the-Dust, Various Locations | 50297 | Streets | Design/Const. | In-house | Bid 4-02-07, Const. 10-31-07 | $50,000 |
| Oversize Reimbursement - Sewer | 50293 | Water Reclamation | Design/Const. | In-house | On-Going 2007 | |
| Oversize Reimbursement - Water | 50295 | Water | Design/Const. | In-house | On-Going 2007 | |
| Parkland Acquisition | 50061 | Parks & Recreation | Land Acquisition | In-house | On-going | $29,212 |
| Parks & Recreation MIP, Various Locations | 50538 | Parks & Recreation | Design/Const. | In-house | On-Going | $70,000 |
| Pavement Marking Paint Contract | 50594-1615 | Public Works | Design/Const. | In-house | Construction Spring & Fall | $100,000 |
| Pavement Marking Tape Contract | 50593-1616 | Public Works | Design/Const. | In-house | Construction Complete 5-31-07 | $50,000 |
| PCC Pavement Maintenance, Haines Avenue | 50445-1626 | Streets | Design/Const. | In-house | Bid 2-21-07, Const. 8-24-07 | $400,000 |
| PCC Pavement Maintenance, Sheridan Lake Rd | 50445-1636 | Streets | Design/Const. | In-house | Bid 4-03-07, Const. 7-03-07 | $400,000 |
| Police Evidence/Traffic/Transit Building | 1637 | Gov't. Buildings | Design | In-house | Consultant Interviews 2-27-07 | $2,000,000 |
| Prairefire Sewer Main | 50659-1594 | Water Reclamation | Construction | Consultant | Construction Complete | $450,000 |
| Promise Road Detention Cell | 50440-1268 | Drainage | Construction | Const. Adv. 4-10-07 Compl. 9-27-07 | $150,000 | |
| QA/QC Investigations - 2007 | 50637-1609 | Streets | Design | Consultant | On-Going | $20,000 |
| Raider Road Watermain Looping | 50475-1601 | Water | Design | In-house | Const. Adv 4-10-07, Compl. 8-17-07 | $175,000 |
| Rapid City Performing Arts Center | 1641 | Gov't. Buildings | Design | Consultant | Conceptual Design 2008 | Unknown |
| Red Rock Water Reservoir | 50284-1184 | Water | Construction | Consultant | Construction Complete 11-02-07 | $3,500,000 |
| Revolving Sanitary Sewer Loan Fund | 50647 | Water Reclamation | Design/Const. | In-house | On-Going | $1,000,000 |
| Robbinsdale Reconstruction Project - Engineering | 50134-1494 | Streets | Design | Consultant | Bid 5-01-07, Const. 11-23-07 | $250,000 |
| Robbinsdale Reconstruction Project - Phase One | 50403 | Streets | Construction | Consultant | Combined with Project 1494 | $2,380,000 |
| Roof Replacements | 50098-1546 | Public Works | Annual | Consultant | Construction Comp. 3-01-07 | $100,000 |
| School Zone Flashers | 50638-1617 | Streets | Construction | In-house | Construction Complete 3-09-07 | $280,000 |
| Sewer Service Lines Matching Funds | 50292 | Water Reclamation | Design/Const. | In-house | On-Going | $50,000 |
| Sidewalk Improvement Project | 50566-1611 | Streets | Design/Const. | In-house | Bid 8-22-07, Const. 9-20-07 | $50,000/Assess |
| Silver St. & Gold St. Utilities Reconstruction | 50418 | Water | Design | Consultant | Consultant Selection 5-07-07 | $2,695,000 |
| South Robbinsdale Channel Improvements | 50556-1485 | Drainage | Construction | Const. Adv. 2-17-07 Compl. 6-18-07 | $146,600 | |
| Sports Facility Grant | 50577 | Parks & Recreation | Annual | In-house | On-going | $50,000 |
| St. Andrew Reconstruction | 50410-1604 | Streets | Design | Consultant | Design 5-11-07, Constr. 9-06-07 | $55,000 |
| Stoney Creek Water Booster & Well House | 50318-953 | Water | Construction | Consultant | Bid 2-27-07, Const. 12-28-07 | $2,100,000 |
| Project Name | Project Number | Department | Scope | Design and Inspection | Project Status | 2007 Estimated Cost |
| Storm Water Phase II Program | 50628 | Drainage | Design/Const. | In-house | On-Going | $40,000 |
| Traffic Signals | 50639-1591 | Streets | Construction | In-house | On-Going | $700,000 |
| Utility Billing Software | 50658-1593 | Public Works | Design | In-house | Implementation Complete 6-01-07 | $325,000 |
| Utility System Master Plan | 50617-1447 | Public Works | Design | Consultant | On-Going 2007 | $1,800,000 |
| Viewfield Detention Dam Outlet Structure | 50412-1486 | Drainage | Design | Consultant | Consultant Selection 5-21-07 | $120,000 |
| W. Chicago Street Lighting | 50366-1560 | Streets | Construction | Consultant | Construction Complete 6-01-07 | $145,000 |
| Water Reservoir Site Selection | 50661 | Water | Design | Consultant | Consultant Selection 10-31-07 | $200,000 |
| Water Rights Acquisition | 50303 | Water | Design/Const. | In-house | On-Going | $100,000 |
| Water Service Line Matching Fund | 50294 | Water | Design/Const. | In-house | On-Going | $15,000 |
| Water Wells No. 13, 14, and 15 | 50454-1578 | Water | Design/Const. | Consultant | Consultant Approved 5-14-07 | $1,775,000 |
| Wonderland Dr. Street & Drainage Reconst. | 50155-1610 | Streets | Design | Consultant | Construction Complete 7-27-07 | $325,000 |
| Wonderland Drive Area 5 Sewer | 50647-1598 | Water Reclamation | Design/Const. | Consultant | On-Hold | $300,000 |
| WRF Digester Repair and Improvements | 50581-1549 | Water Reclamation | Design/Const. | Consultant | Design 5-25-07 - Const. 2008 | $375,000 |